Logistics
Open pit mine Iretsky
Coal production is carried out at the largest deposits of the Golumetsky coal-bearing area in the center of the Irkutsk coal basin
Cheremhovo railway station
At present, the construction of our own loading facilities is underway at the Cheremkhovo station with a design capacity of 2 million tons per year
– Stage 1 1 million tons 45 railcars per day
– Stage 2 2 million tons 71 railcars per day
The project includes:
1. Organization of a site for the temporary storage of 100 000 tons of coal.
2. The front of the loading is designed for 20 rail cars.
3. Installation of rail and truck scales.
4. Length of shunting railways. tracks allow us to receive 36 empty railcars from the Cheremkhovo station.
The planned date for the synchronization of public and non-public tracks is until 01.10.2020. The completion of construction and the start of shipments are planned to begin by the end of 2020.
The planned output to the planned capacity for shipment is 2021, in accordance with Stage 1 of the Technical Specifications of Russian Railways.
Kasianovka railway station
From the site coal is delivered by road to the Kasianovka railway station of the East Siberian Railway
Zabaikalsk railway station
Delivery to China is carried out from Kasianovka railway station through the Zabaikalsk-Manchuria border crossing
Grodekovo railway station
Delivery to China is carried out from Kasyanovka railway station through the Grodekovo-Suifenghe border crossing
Vostochny Port
The cargo arrives at the Nakhodka-Vostochnaya railway station of the Far Eastern Railway. Delivery to Japan, Korea, and Taiwan is carried out through Vostochny Port using modern conveyor systems and ship loading machines
Kamishovaya railway station
Delivery to China is carried out from Kasyanovka station through the Kamyshovaya-Hunchunnan border crossing
AO Rosterminalugol
The cargo arrives at the Luzhskaya station of the Oktyabrskaya Railway. Delivery to Europe and North Africa is carried out through AO “Rosterminalugol”